Strategia Obywatelska
Manufacturing

Implementation of an executive system for a print shop

We introduced concrete indicators for 5 shift managers, which shortened order fulfillment time. The percentage of on-time deliveries rose from 78% to 91%.

+13% punctuality
ClientDrukarnia Offsetowa Echo
IndustryManufacturing
TimelineFebruary–August 2024

Drukarnia Offsetowa Echo struggled with chaos in production management. We introduced clear reporting rules that allowed for avoiding downtime on the shop floor.

Change managementLeanReportingOperational audit

The challenge

The main problem was the lack of information flow between shifts. Each of the 5 managers kept notes in a different way, which led to errors in orders. During the first 2 weeks of analysis, we noticed that the average waiting time for a decision to start printing was as much as 4.2 hours.

The situation was made worse by downtime resulting from a lack of raw materials, which no one ordered on time. Customers started reporting delays, which in this industry ends in a quick loss of margin. Trust is built on facts, and here system data clearly showed a 12% drop in efficiency compared to the previous year.

Our approach

Civil Strategy focused on simplicity. We abandoned extensive software the staff wasn't ready for and implemented clear task cards for each station. Our team conducted training for 5 managers, establishing that every delay over 30 minutes must be recorded in the register.

We organize the power structure, so we clearly defined responsibility for every batch of materials. We introduced morning briefings lasting a maximum of 15 minutes, during which we discuss only current orders and production bottlenecks.

The solution

We designed a visual system on the production floor. Each machine gained a status board, thanks to which you can immediately see if work is going according to plan. We speak directly about profits, so we invested in a simple SMS notification system for the logistics department regarding low paper stock levels.

Additionally, we implemented a new shift handover protocol. Now the manager finishing work has 20 minutes to complete a report, and the manager starting – 10 minutes to familiarize themselves with priorities. This eliminated unnecessary questions and searching for documentation.

Results

After 6 months of work, Drukarnia Offsetowa Echo achieved operational stability. Thanks to new habits, we reduced the number of erroneous issues and improved the morale of the team, who stopped working in constant stress.

+13%
Increase in on-time deliveries
2.4h
Average reduction in startup time
-27%
Reduction of production waste

Timeline

  1. February 2024
    Audit of information flow on the floor
  2. March 2024
    Implementation of a task card system
  3. April 2024
    Manager training on reporting
  4. June 2024
    Optimization of raw material ordering process
  5. August 2024
    Final assessment of system effectiveness

"I was skeptical about changes because the crew has been here for years. It turned out that all it took was to organize one report card for the chaos to disappear. It works, simple as that."

Marek Zieliński Production Director, Drukarnia Offsetowa Echo September 2024